Full power at Butendiek offshore wind farm

- Bringing the 80th wind turbine into operation seals the \"success story Butendiek\"
- the 288 MW North Sea windfarm that supplies approximately 370,000 households with renewable energy

Bremen - Bringing the 80th and thus final wind turbine into operation, the construction of the offshore wind farm Butendiek is now complete. Joint owners wpd, Marguerite Fund, Siemens Financial Services, Industriens Pension, Pensionskassernes Administration (PKA), CDC Infrastructure and ewz (Elektrizitätswerk der Stadt Zürich) are therefore pleased to announce, that the 288 MW wind farm, located in the North Sea, is now in full operation. wpd, the Bremen wind developer and operator is responsible for the construction and operation phases.

In March 2014, offshore works began. All foundations, cables and the substation were installed according to schedule during the last year. Mid-June, the 80th wind turbine was installed and now brought into operation.

\"Already eleven months after start of construction, the first wind turbine fed electricity into the public grid. This makes Butendiek the fastest established offshore project\", says project director Martin Lehnhoff.

\"Thanks to the intensive collaboration of all parties involved, the Butendiek project became a real success story in many ways\", says Achim Berge Olsen, Managing Director of OWP Butendiek GmbH & Co. KG and wpd offshore GmbH. \"The lowest value has been measured regarding noise emissions during installation and the 1.3 bn euro OWF Butendiek project has been completed on schedule and within budget. From now on, OWF Butendiek is able to supply 370,000 households with green energy.\"


Basic data offshore wind farm Butendiek:
. 80 wind turbines with a total output of 288 MW
. Location: North Sea, approximately 32 km to the west of Sylt
. Water depth: about 20 meters
. Investors: Marguerite Fund, Siemens Financial Services, Industriens Pension, Pensionskassernes Administration (PKA), CDC Infrastructure, ewz (Elektrizitätswerk der Stadt Zürich) and wpd
. Collaboration with notable suppliers: Siemens (Siemens SWT 3.6-120 Turbines), Ballast Nedam (Foundations), VBMS (Cabling ), Cofely Fabricom GdF Suez (Offshore Substation)
. Supply of approximately 370,000 households with green energy
. Total amount invested: 1.3 billion euro


Bremen, August 6, 2015


Publication and Reprint free of charge; please send a voucher copy to
wpd AG.


Media contacts:

Christian Schnibbe
Head of Communication
Tel: +49 (421) 16866-2500
E-mail: c.schnibbe@wpd.de


wpd AG
Stephanitorsbollwerk 3 (Haus LUV)
28217 Bremen

Internet: http://www.wpd.de



Online press kit - all press releases from DE239541638


Press photos for editorial use only
Note: For the content of this press release the issuer / publisher of the release is »DE239541638« responsible.

The press release "Full power at Butendiek offshore wind farm" von DE239541638 is also available in the following languages:


More press releases from wpd GmbH


About wpd GmbH

wpd was founded in Bremen in 1996 and has become one of the leading developers and operators of onshore wind and solar farms in Europe. The group of companies consists of wpd GmbH (project developer and operator), wpd windmanager (commercial management and technical operations) and Deutsche Windtechnik (maintenance and engineering).

With 3,700 employees worldwide, wpd has implemented projects with 2,630 wind turbines and a total capacity of 6,110 MW, as well as solar energy projects with a capacity of 35 MW.

Besides developing projects in-house, wpd also undertakes project partnerships, commercial construction, contracting, project financing through to completion and the operation of wind and solar energy plants.

In addition to its home market in Germany, wpd is also active in the main wind and solar markets in Europe, in North and South America, and in various countries in the rapidly growing Asian market. The company has built a global project pipeline of 13,870 MW of onshore wind and 2,300 MWp of solar PV. Today, wpd is active in 29 countries worldwide.

www.wpd.de

Press contact at wpd GmbH

Christian Schnibbe
Mail: c.schnibbe@wpd.de
Phone: +49 (0)421 / 16866-10

Christian Schnibbe

Press contact

Christian Schnibbe

Christian Schnibbe
wpd GmbH
Mail: c.schnibbe@wpd.de
Phone: +49 (0)421 / 16866-10