Deutsche Windtechnik takes stock one year after deploying its new maintenance campaign at the Nordergründe offshore wind farm: downtimes significantly reduced by synergies
Deutsche Windtechnik was able to reduce downtimes at the Nordergründe offshore wind farm by 28.5 percent in 2021 by using maintenance campaigns focused on synergies.
© Deutsche Windtechnik AGBremen (renewablepress) - By realigning its maintenance campaign at the offshore wind farm Nordergründe, Deutsche Windtechnik, which is the only independent full-service provider in the offshore wind energy sector, was able to reduce maintenance-related downtimes by 28.5 percent in 2021 compared to the previous year. Following the insolvency of the system manufacturer, maintenance work for the 18 Senvion 6.2M 126 turbines was still carried out separately from other maintenance work in 2020. In 2021, however, it was possible to combine all of the specialised tasks at the wind farm into one maintenance campaign. In addition, the multi-competent team for troubleshooting tasks was able to significantly increase efficiency.
The central element of the new maintenance strategy was the simultaneous deployment of two specialised service teams for the first time as part of the regular annual maintenance campaign: While one team with expertise in turbine maintenance was doing its job, the second team with specialists for the Balance of Plants was working on the transition piece and the foundation at the same time. This simultaneous work has not only reduced the downtime of the turbines but has also reduced activities such as the number of transfers from the CTV to the boat landing, which have been halved from 288 to 144 for the entire wind farm.
Teams with a blend of expertise in different areas for flexible troubleshooting
In addition, another service team dedicated to troubleshooting tasks was deployed at the wind farm the whole time. This blended team consisted of three technicians, each with different competence profiles, so that errors in various components of the wind turbine, the transition piece or the substation could be corrected quickly and flexibly, and this opened up further synergies. The costs for the troubleshooting deployments were allocated proportionally to the Balance of Plants or the service contract, depending on the reason for the work.
Benefits from synergies are also leveraged at other offshore wind farms
"The Nordergründe offshore wind farm clearly demonstrates the advantages for the operator by planning maintenance campaigns from a single source," said Matthias Brandt, Director of Deutsche Windtechnik. "Today, there is an increasing trend towards maintenance and service operations that are organised in a task-specific manner that optimises logistics and personnel to take advantage of time and cost synergies." Another example of this development are the DanTysk and Sandbank wind farms. Deutsche Windtechnik is responsible for a large portion of the necessary work at these wind farms, including maintenance and repair work for 152 turbines, maintenance for the transition pieces, the lifts and the cranes, and inspections.
About Deutsche Windtechnik AG
Bremen-based Deutsche Windtechnik AG offers a single-source full technical maintenance package for wind turbines in Europe, the USA and Taiwan. The company operates both onshore and offshore. More than 2,000 employees provide service for over 7,500 wind turbines worldwide under permanent maintenance contracts (basic and full maintenance). The company's system engineering focuses on Vestas, Siemens, Nordex, Senvion, Fuhrländer, Gamesa, Enercon and GE turbines.
Download press photo:
https://www.renewablepress.com/press-images/deutsche-windtechnik/c10d7_1707_JM_Offshore_Nordergruende_13.jpg
Caption: Deutsche Windtechnik was able to reduce downtimes at the Nordergründe offshore wind farm by 28.5 percent in 2021 by using maintenance campaigns focused on synergies.
© Deutsche Windtechnik AG
Bremen, 16 May 2022
Publication and Reprint free of charge; please send a voucher copy to Deutsche Windtechnik AG.
Attention editorial offices - For further questions please contact:
Media contact:
Karola Kletzsch
Corporate Communication
Deutsche Windtechnik AG
Tel: + 49 (0)421 – 69 105 330
Mob: + 49 (0)172 - 263 77 89
Fax: + 49 (0)421 - 691 05 499
E-Mail: k.kletzsch@deutsche-windtechnik.com
Deutsche Windtechnik AG
Stephanitorsbollwerk 1 (Haus LEE)
28217 Bremen
Tel: +49 (0)421 69105-0
Fax: +49 (0)421 69105-499
E-Mail: info@deutsche-windtechnik.com
Internet: https://www.deutsche-windtechnik.com
Online press kit - all press releases from DE252570942
Press photos for editorial use only
Note: For the content of this press release the issuer / publisher of the release is »DE252570942« responsible.
The press release "Deutsche Windtechnik takes stock one year after deploying its new maintenance campaign at the Nordergründe offshore wind farm: downtimes significantly reduced by synergies" von DE252570942 is also available in the following languages:
More press releases from Deutsche Windtechnik AG
- Unique in Germany: Deutsche Windtechnik, the Bremen Chamber of Commerce and the Friedehorst Vocational Training Centre are launching a training exam for the profession “Qualified Electrician in Industry (IHK)” in English
- Deutsche Windtechnik is merging its two largest onshore service units in Germany
- Deutsche Windtechnik's inspection body is one of the first to use drone technology on a large scale for periodic inspections of the rotor blades at the Butendiek offshore wind farm
- Deutsche Windtechnik has established an offshore unit in Poland
- Deutsche Windtechnik to begin providing maintenance for Enercon wind turbines in France
- Deutsche Windtechnik wins a further tender for offshore ADLS
- Deutsche Windtechnik begins providing Enercon-service in Benelux – Long-term full maintenance contract signed with Eneco Wind Belgium
- Deutsche Windtechnik has more than doubled the availability of the Adwen turbines at the alpha ventus offshore wind farm by implementing an optimised maintenance concept
- Deutsche Windtechnik Service Shows Strong Growth
- wpd windmanager, psm and Deutsche Windtechnik: Growing together to grow together
About Deutsche Windtechnik AG
Deutsche Windtechnik AG offers a single-source full technical maintenance package for wind turbines in Europe, North America and Taiwan. The company operates both onshore and offshore.
More than 7,500 wind turbines with a rated output of more than 12 GW are serviced by over 2,000 employees as part of permanent maintenance contracts (basic and full maintenance). Its system engineering focuses on Vestas/NEG Micon, Siemens/AN Bonus, Nordex, Senvion, Fuhrländer, Gamesa and Enercon turbines.
Deutsche Windtechnik take occupational safety and environmental protection very seriously, so all of their services are certified in accordance with ISO 9001:2015, BS OHSAS 18001:2007, ISO 14001:2015.
Press contact at Deutsche Windtechnik AG
Karola Kletzsch
Mail: k.kletzsch@deutsche-windtechnik.com
Phone: +49 (0)421 - 69105 330